Explore Westonci.ca, the premier Q&A site that helps you find precise answers to your questions, no matter the topic. Get immediate and reliable answers to your questions from a community of experienced experts on our platform. Explore comprehensive solutions to your questions from a wide range of professionals on our user-friendly platform.
Sagot :
Answer:
9 labours
Step-by-step explanation:
In order to solve this, we must know which kind of proportionality is this. There are two types of proportions, direct and indirect/inverse proportions. In direct proportion, if one quantity increases, the other quantity also increases.
In indirect proportion, if one quantity increases, the other decreases and vice versa.
As per this question, we know if the number of labour increases, the number of days to complete a work decreases, thus proving that this is an indirect/inverse proportion.
6 labours => 12 days
x labours => 8 days
Since its an inverse proprotion, multiply 6 with 12, and x with 8.
8x = 6 × 12
x = [tex]\frac{6*12}{8}[/tex]
∴ x = 9 labours
Visit us again for up-to-date and reliable answers. We're always ready to assist you with your informational needs. Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. Stay curious and keep coming back to Westonci.ca for answers to all your burning questions.