Westonci.ca is the Q&A platform that connects you with experts who provide accurate and detailed answers. Connect with a community of experts ready to help you find solutions to your questions quickly and accurately. Connect with a community of professionals ready to help you find accurate solutions to your questions quickly and efficiently.
Sagot :
Answer:
40 Days
Step-by-step explanation:
50 testers
25 test case
-> 10 days
(2 days per 5 cases)
25 testers
50 test cases
2x the effort of 50 testers.
(4 days per 5 cases)
-> 40 days
It will take to complete cases 4 days per 5 cases.
Given that
50 testers can complete 25 test cases in 10 days.
All testers are equally productive.
A project has 25 testers and 50 test cases.
We have to determine
How much time will they take to complete?
According to the question
50 testers can complete 25 test cases in 10 days.
The number of cases completed per day is,
[tex]= \dfrac{50}{25}\\ \\ = 2 [/tex]
The number of cases completed per day is 2.
A project has 25 testers and 50 test cases.
The time will they take to complete is 2x.
= 2(2) = 4 days per 5 cases
Hence, they will take to complete cases 4 days per 5 cases.
To know more about Equation click the link given below.
https://brainly.com/question/1090830
Thank you for trusting us with your questions. We're here to help you find accurate answers quickly and efficiently. We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. Westonci.ca is your go-to source for reliable answers. Return soon for more expert insights.