Welcome to Westonci.ca, the place where your questions find answers from a community of knowledgeable experts. Join our Q&A platform to get precise answers from experts in diverse fields and enhance your understanding. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform.
Sagot :
Answer:
40 Days
Step-by-step explanation:
50 testers
25 test case
-> 10 days
(2 days per 5 cases)
25 testers
50 test cases
2x the effort of 50 testers.
(4 days per 5 cases)
-> 40 days
It will take to complete cases 4 days per 5 cases.
Given that
50 testers can complete 25 test cases in 10 days.
All testers are equally productive.
A project has 25 testers and 50 test cases.
We have to determine
How much time will they take to complete?
According to the question
50 testers can complete 25 test cases in 10 days.
The number of cases completed per day is,
[tex]= \dfrac{50}{25}\\ \\ = 2 [/tex]
The number of cases completed per day is 2.
A project has 25 testers and 50 test cases.
The time will they take to complete is 2x.
= 2(2) = 4 days per 5 cases
Hence, they will take to complete cases 4 days per 5 cases.
To know more about Equation click the link given below.
https://brainly.com/question/1090830
Visit us again for up-to-date and reliable answers. We're always ready to assist you with your informational needs. Thank you for your visit. We're dedicated to helping you find the information you need, whenever you need it. We're here to help at Westonci.ca. Keep visiting for the best answers to your questions.