At Westonci.ca, we connect you with the best answers from a community of experienced and knowledgeable individuals. Connect with professionals on our platform to receive accurate answers to your questions quickly and efficiently. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform.
Sagot :
Answer:
40 Days
Step-by-step explanation:
50 testers
25 test case
-> 10 days
(2 days per 5 cases)
25 testers
50 test cases
2x the effort of 50 testers.
(4 days per 5 cases)
-> 40 days
It will take to complete cases 4 days per 5 cases.
Given that
50 testers can complete 25 test cases in 10 days.
All testers are equally productive.
A project has 25 testers and 50 test cases.
We have to determine
How much time will they take to complete?
According to the question
50 testers can complete 25 test cases in 10 days.
The number of cases completed per day is,
[tex]= \dfrac{50}{25}\\ \\ = 2 [/tex]
The number of cases completed per day is 2.
A project has 25 testers and 50 test cases.
The time will they take to complete is 2x.
= 2(2) = 4 days per 5 cases
Hence, they will take to complete cases 4 days per 5 cases.
To know more about Equation click the link given below.
https://brainly.com/question/1090830
Thanks for stopping by. We strive to provide the best answers for all your questions. See you again soon. Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. Stay curious and keep coming back to Westonci.ca for answers to all your burning questions.