Welcome to Westonci.ca, where curiosity meets expertise. Ask any question and receive fast, accurate answers from our knowledgeable community. Get quick and reliable solutions to your questions from knowledgeable professionals on our comprehensive Q&A platform. Experience the ease of finding precise answers to your questions from a knowledgeable community of experts.

A job takes 30 men for 15 days to complete. How many men need to increase to do the same job in 10 days?

Sagot :

Answer:

45 men

Step-by-step explanation:

A job takes 30 men for 15 days to complete so it takes x men to do the same job in 10 days

30(15) = x(10)

450 = 10x

x = 450/10

x = 45

Answer:

45 days

Step-by-step explanation:

30men=15days

1man=15×30

1man=450days

10men=450÷10

10men=45days

I think that's it