Welcome to Westonci.ca, your one-stop destination for finding answers to all your questions. Join our expert community now! Explore thousands of questions and answers from a knowledgeable community of experts on our user-friendly platform. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform.
Sagot :
Answer:
44 hours
Step-by-step explanation:
Topic of this question: Creating and Solving Equations, Rates, and Proportions
Method 1: Creating and Solving Equations
Step 1: Find the amount drilled per hour
To do this, we have to divide the amount drilled by the number of hours it took to drill and find how much is being drilled per hour.
(I know it's a mouthful)
-72ft = 24x, where x is the amount drilled per hour
-72ft ÷ 24 = x
-3ft = x
-3ft per hour
Step 2: Find how many hours it takes to drill to -132 ft
Since we know the rate of drilling per hour, we can divide the target amount by the amount drilled per hour
-132 ÷ -3 = y, where y is the number of hours it takes
44 = y
y = 44
It will take a total of 44 hours to drill to -132 ft
Method 2: Proportions
We can set up a proportion like this, where we know that it takes 24 hours to drill 72 ft, but we don't know how long it takes to drill 132 feet
[tex]\frac{-72}{24} = \frac{-132}x[/tex]
Cross multiply
[tex]-72x = 24 * -132[/tex]
Simplify
[tex]-72x = -3168\\[/tex]
Divide both sides by -72
[tex]x = -3,168/-72[/tex]
[tex]x = 44[/tex]
It will take a total of 44 hours to dig to -132 ft
-Chetan K
We hope this information was helpful. Feel free to return anytime for more answers to your questions and concerns. Thank you for choosing our platform. We're dedicated to providing the best answers for all your questions. Visit us again. Thank you for choosing Westonci.ca as your information source. We look forward to your next visit.