Discover the best answers at Westonci.ca, where experts share their insights and knowledge with you. Explore our Q&A platform to find in-depth answers from a wide range of experts in different fields. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform.

The total output from a production system in one day is 500 units and the total labor necessary to produce the 500 units is 350 hours. Using the appropriate productivity measure, which of the following numbers represents the resulting productivity ratio?.

Sagot :

Given what we know, we can confirm that the resulting productivity ratio for the situation described in the question will be 1.43:1.

How can we calculate the productivity ratio?

To arrive at this number we must first clarify that the productivity ratio is a metric used to measure the amount of product that is produced on an hourly work basis. Therefore, to calculate this, we take the total product produced in the day and divide it by the total hours of work needed to create it. Here, that means dividing 500 by 350 to arrive at the ratio of 1.43:1.

Therefore, we can confirm that by dividing the products created by the working hours needed to create the product, we can arrive at the productivity ratio which is 1.43:1.