Westonci.ca makes finding answers easy, with a community of experts ready to provide you with the information you seek. Get detailed answers to your questions from a community of experts dedicated to providing accurate information. Explore comprehensive solutions to your questions from knowledgeable professionals across various fields on our platform.

When you link two tasks using the Link Tasks feature on the Task tab, Microsoft Project creates a _____ link.

Sagot :

Lanuel

A finish-to-start link is created by Microsoft Project when you link two tasks using the Link Tasks feature on the Task tab.

What is Microsoft Project?

Microsoft Project can be defined as a project management software product that is designed an developed by Microsoft Inc., so as to assist project managers in achieving the following project tasks:

  • Developing a schedule.
  • Analyzing workloads.
  • Assigning resources to tasks.
  • Tracking project progress.
  • Managing their project budget.

On Microsoft Project, a finish-to-start link is primarily created when you link two tasks using the Link Tasks feature on the Task tab.

Read more on project management here: https://brainly.com/question/6500846