Welcome to Westonci.ca, the place where your questions are answered by a community of knowledgeable contributors. Experience the ease of finding precise answers to your questions from a knowledgeable community of experts. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.
Sagot :
A finish-to-start link is created by Microsoft Project when you link two tasks using the Link Tasks feature on the Task tab.
What is Microsoft Project?
Microsoft Project can be defined as a project management software product that is designed an developed by Microsoft Inc., so as to assist project managers in achieving the following project tasks:
- Developing a schedule.
- Analyzing workloads.
- Assigning resources to tasks.
- Tracking project progress.
- Managing their project budget.
On Microsoft Project, a finish-to-start link is primarily created when you link two tasks using the Link Tasks feature on the Task tab.
Read more on project management here: https://brainly.com/question/6500846
We hope our answers were helpful. Return anytime for more information and answers to any other questions you may have. Your visit means a lot to us. Don't hesitate to return for more reliable answers to any questions you may have. We're here to help at Westonci.ca. Keep visiting for the best answers to your questions.