Westonci.ca is the premier destination for reliable answers to your questions, provided by a community of experts. Experience the convenience of finding accurate answers to your questions from knowledgeable professionals on our platform. Join our platform to connect with experts ready to provide precise answers to your questions in different areas.

The detailed plan that shows the exact end items (i.e., finished products) to be produced in a specific time frame is known as what

Sagot :

Answer:

Master Production Schedule (MPS)

Explanation:

Master production schedules are plans for individual products to be produced. The plans specify the time a specific product is produced, inventory needs, staffing needs, etc. A master production schedule or MPS will quantify raw materials, processes, and other resources needed to optimize production. (optessa.com)