Westonci.ca is the Q&A platform that connects you with experts who provide accurate and detailed answers. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform. Connect with a community of professionals ready to provide precise solutions to your questions quickly and accurately.


It takes 12 men 5 days to complete a job. Work out how many days it would take 3 men to complete the same job.

Sagot :

Esther

Answer:

20 days

Step-by-step explanation:

It takes 12 men 5 days to complete a job. Work out how many days it would take 3 men to complete the same job.

12 * 5 = 60

60/3 = 20

It will take 3 men 20 days to do the same job