At Westonci.ca, we provide reliable answers to your questions from a community of experts. Start exploring today! Explore a wealth of knowledge from professionals across different disciplines on our comprehensive platform. Get quick and reliable solutions to your questions from a community of experienced experts on our platform.


It takes 12 men 5 days to complete a job. Work out how many days it would take 3 men to complete the same job.


Sagot :

Esther

Answer:

20 days

Step-by-step explanation:

It takes 12 men 5 days to complete a job. Work out how many days it would take 3 men to complete the same job.

12 * 5 = 60

60/3 = 20

It will take 3 men 20 days to do the same job