Welcome to Westonci.ca, where your questions are met with accurate answers from a community of experts and enthusiasts. Connect with a community of experts ready to help you find accurate solutions to your questions quickly and efficiently. Discover detailed answers to your questions from a wide network of experts on our comprehensive Q&A platform.

you work on a concrete crew starting a construction project. once the pouring begins, it must continue nonstop until it is completed. your crew will work an 8-hour shift along with two other crews. The total project requires 175,000 yards of concrete. your supervisor estimates that each crew will pour around 1200 yards per hour. how many consecutive days should you plan to work on this project?
A. 3
B. 6
C. 18
D. 27
E. 146

ACT WORKKEYS 2022