Westonci.ca is your go-to source for answers, with a community ready to provide accurate and timely information. Connect with a community of professionals ready to help you find accurate solutions to your questions quickly and efficiently. Our platform provides a seamless experience for finding reliable answers from a network of experienced professionals.

Select the correct answer.
Thomas, a senior manager at a manufacturing firm, is coming up with ideas for a new product. Thomas has made a list of the following tasks that form a part of this project, along with their respective durations.

Create questionnaires to interview potential customers (7 days)
Find existing information about the market from online sources and trade journals (6 days)
Interview the respondents with the help of the questionnaire (10 days)
Design a new product according to the information obtained through the interviews (30 days)
If Thomas conducts a Critical Path Analysis to schedule these activities, what is the most likely duration that the activities will take to be completed?
A.
50 days
B.
40 days
C.
57 days
D.
47 days
E.
67 days


Sagot :

Answer: I believe it is "C" 57 days.

Step-by-step explanation: Add all the dates together and round to the nearest number of days.

We hope this information was helpful. Feel free to return anytime for more answers to your questions and concerns. Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. Westonci.ca is here to provide the answers you seek. Return often for more expert solutions.