Get reliable answers to your questions at Westonci.ca, where our knowledgeable community is always ready to help. Get quick and reliable answers to your questions from a dedicated community of professionals on our platform. Experience the ease of finding precise answers to your questions from a knowledgeable community of experts.

a contractor hires 150 men to pave Philip Goldson highway in 30 days. How many men will he hire to do the same work in 20 days?​

Sagot :

Answer:

225 men

This conversion leads to the answer:

  • 30 days → 150 men
  • 1 days → (150 *30) men
  • 1 days → 4500 men
  • 20 days → (4500/20) men
  • 20 days → 225 men