Discover a wealth of knowledge at Westonci.ca, where experts provide answers to your most pressing questions. Our platform connects you with professionals ready to provide precise answers to all your questions in various areas of expertise. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform.

Johnson can tile a 100 square foot floor in 7 hours. Nathan can tile the same area in 9 hours. Enter an equation that can be used to find the time in hours,t it would take Johnson and Nathan to tile a 100 square foot area together.

Sagot :

The equation that can be used to find the time t, in hours,  it would take Johnson and Nathan to tile a 100 square foot area together is 3.9375 hours, which approximates to 4 hours.

How are number of people to time needed to complete a task related?

More people to do a task means less time it will take.

Less people to do a task means more time it will take.

Thus, they are inversely related.

If x men take y time for a work,(assume all men have same strength)

We can define a constant as "Manpower" needed for doing that specific work.

Let we define:

Manpower needed for a work = y + y + y + .. + y = Time per man × count of men

Manpower needed for a work = xy

For this case, we're specified that:

  • Work in consideration = Tiling 100 sq. foot floor
  • Time it takes by Johnson to do this work = 7 hours
  • Time it takes by Nathan to do this work = 9 hours

So, we see that strength of Johnson and Nathan are different.

Let the general manpower (from some frame of a general public or any third frame) needed by this work be M.

Then, Johnson delivers M manpower in 7 hours or M/7 manpower in one hour.

In the similar way, Nathan delivers M/9 manpower per hour.

Thus, if Nathan and Johnson work together, they can deliver: [tex]\dfrac{M}{9} + \dfrac{M}{7} = M\dfrac{9+7}{63} = \dfrac{16M}{63}[/tex] manpower per hour.

Let it takes them together h hours to complete the work.
That means, in 'h' hours, their together work power will accumulate to M manpower.

Or, we can say:

[tex]h \times \dfrac{16M}{63} = M\\\\h = \dfrac{63M}{16M} = \dfrac{63}{16} = 3.9375[/tex]

Thus, the equation that can be used to find the time t, in hours,  it would take Johnson and Nathan to tile a 100 square foot area together is 3.9375 hours, which approximates to 4 hours.