Welcome to Westonci.ca, the ultimate question and answer platform. Get expert answers to your questions quickly and accurately. Get quick and reliable answers to your questions from a dedicated community of professionals on our platform. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform.

A solar energy project is expected to have capital costs of $995,000, average yearly operating costs of $175,000, and a lifetime of 25 years. If the total production during the lifetime of the project is 89,500,000 kwh, what is the levelized cost of energy (lcoe)?(1 point)

Sagot :

The Levelized Cost of Energy (LCOE) gotten from the given parameters is; $0.06 per kWh

How to find Levelized Cost?

We aregiven;

Capital costs of the Solar Energy Project = $ 995,000.

Average yearly operating costs = $ 175,000.

We are told that the project is estimated to run for 25 years, producing a total 89,500,000 kWh.

Formula for Levelized Cost of Energy is;

LCOE = (Capital Costs + (Average yearly operating Costs * Number of project years))/Total Production

LCOE = (995000 + (175000 * 25))/89500000

LCOE = $0.06 per kWh

Read more about Levelized Cost at; https://brainly.com/question/13943520

#SPJ1

Thanks for using our service. We aim to provide the most accurate answers for all your queries. Visit us again for more insights. Thanks for using our service. We're always here to provide accurate and up-to-date answers to all your queries. Discover more at Westonci.ca. Return for the latest expert answers and updates on various topics.