Welcome to Westonci.ca, your one-stop destination for finding answers to all your questions. Join our expert community now! Explore a wealth of knowledge from professionals across different disciplines on our comprehensive platform. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.

A capital budgeting project is expected to have the following cash flows: Year Cash Flows 0 -$850,000 1 $300,000 2 $400,000 3 $500,000 What is the project's net present value at an 18% required rate of return

Sagot :

The capital budgeting project's net present value at an 18% required rate of return is ($4,200).

What is the net present value?

The net present value represents the net discounted value of cash inflows after subtracting the present value of cash outflows.

The net present value can be determined by determining the present values of cash inflows and outflows and netting the two values.

Data and Calculations:

Required rate of return = 18%

Project period = 3 years

Year    Cash Flows    PV Factor        Present Value

0         -$850,000            1                    -$850,000 ($850,000 x 1)

1           $300,000         0.847               $254,100 ($300,000 x 0.847)

2         $400,000          0.718               $287,200 ($400,000 x 0.718)

3         $500,000        0.609               $304,500 ($500,000 x 0.609)

Net present value                                ($4,200)

Thus, the capital budgeting project's net present value at an 18% required rate of return is ($4,200).