Welcome to Westonci.ca, the ultimate question and answer platform. Get expert answers to your questions quickly and accurately. Discover detailed answers to your questions from a wide network of experts on our comprehensive Q&A platform. Get quick and reliable solutions to your questions from a community of experienced experts on our platform.
Sagot :
The capital budgeting project's net present value at an 18% required rate of return is ($4,200).
What is the net present value?
The net present value represents the net discounted value of cash inflows after subtracting the present value of cash outflows.
The net present value can be determined by determining the present values of cash inflows and outflows and netting the two values.
Data and Calculations:
Required rate of return = 18%
Project period = 3 years
Year Cash Flows PV Factor Present Value
0 -$850,000 1 -$850,000 ($850,000 x 1)
1 $300,000 0.847 $254,100 ($300,000 x 0.847)
2 $400,000 0.718 $287,200 ($400,000 x 0.718)
3 $500,000 0.609 $304,500 ($500,000 x 0.609)
Net present value ($4,200)
Thus, the capital budgeting project's net present value at an 18% required rate of return is ($4,200).
Learn more about the net present value at https://brainly.com/question/13228231
#SPJ1
We hope our answers were helpful. Return anytime for more information and answers to any other questions you may have. Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. We're here to help at Westonci.ca. Keep visiting for the best answers to your questions.