Welcome to Westonci.ca, your ultimate destination for finding answers to a wide range of questions from experts. Explore comprehensive solutions to your questions from a wide range of professionals on our user-friendly platform. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.

In the EST graph above, what is the required time to complete task E?​

In The EST Graph Above What Is The Required Time To Complete Task E class=

Sagot :

Answer:

  8 time periods

Step-by-step explanation:

This Earliest Start Time graph shows task completion times on the arrow out of the bubble representing the task.

__

Task E completes in 8 time periods.

_____

Additional comment

The number in parentheses inside the bubble is the number of time periods before the task can be started, at the earliest. That number in the Finish bubble is the earliest the project can be completed.