Westonci.ca is the premier destination for reliable answers to your questions, provided by a community of experts. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform.

Kay Company budgets overhead cost of $4,104,000 for the next year. The company uses direct labor hours as its overhead allocation base. If 90,000 direct labor hours are planned for the next year, how much overhead would be assigned to a product requiring 5 direct labor hours

Sagot :

Based on the fact that Kay Company will use direct labor hours as its overhead allocation base, the overhead for a product with 5 labor hours is $228.

What is the overhead assigned to the product?

This can be found as:

= Total overhead cost / Number of labor hours x Product labor hours

Solving gives:

= 4,104,000 / 90,000 x 5

= 45.6 x 5

= $228