Westonci.ca is the Q&A platform that connects you with experts who provide accurate and detailed answers. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform.

The following diagram shows a 4-step process that begins with Operation 1 and ends with Operation 4.

The Following Diagram Shows A 4step Process That Begins With Operation 1 And Ends With Operation 4 class=

Sagot :

Based on the operations and their times, the capacity of this process is 10 per hour and the action that would yield the greatest increase would be 2. increase operation 2 by 14%.

What is the capacity of the process?

The capacity of the process is the least operation time in the process which is 10/ hr.

How can we get the greatest increase in process capacity?

Check all the alternatives given. The alternative with the lowest capacity is best.

Increase operation 1 by 12%:

= 11 x (1 + 12%)

= 12.32 per hour

Increase operation 2 by 14%:

= 10 x (1 + 14%)

= 11.4 per hour

Increase operation 3 by 10%:

= 12 x (1 + 10%)

= 13.2 per hour

The best alternative is therefore to increase operation 2 by 14%.