Discover answers to your questions with Westonci.ca, the leading Q&A platform that connects you with knowledgeable experts. Join our platform to connect with experts ready to provide precise answers to your questions in various areas. Explore comprehensive solutions to your questions from a wide range of professionals on our user-friendly platform.

The following diagram shows a 4-step process that begins with Operation 1 and ends with Operation 4.

The Following Diagram Shows A 4step Process That Begins With Operation 1 And Ends With Operation 4 class=

Sagot :

Based on the operations and their times, the capacity of this process is 10 per hour and the action that would yield the greatest increase would be 2. increase operation 2 by 14%.

What is the capacity of the process?

The capacity of the process is the least operation time in the process which is 10/ hr.

How can we get the greatest increase in process capacity?

Check all the alternatives given. The alternative with the lowest capacity is best.

Increase operation 1 by 12%:

= 11 x (1 + 12%)

= 12.32 per hour

Increase operation 2 by 14%:

= 10 x (1 + 14%)

= 11.4 per hour

Increase operation 3 by 10%:

= 12 x (1 + 10%)

= 13.2 per hour

The best alternative is therefore to increase operation 2 by 14%.

Find out more on process capacity at https://brainly.com/question/20396505.