At Westonci.ca, we connect you with the answers you need, thanks to our active and informed community. Our Q&A platform provides quick and trustworthy answers to your questions from experienced professionals in different areas of expertise. Discover detailed answers to your questions from a wide network of experts on our comprehensive Q&A platform.
Sagot :
Completing the Cost of Goods Manufactured Schedule for Riverbed Company is as follows:
Cost of Goods Manufactured Schedule
Work in process (1/1) $222,600
Direct materials:
Raw materials inventory (1/1) $ 47,300
Add: Raw materials purchases 168,000
Total raw materials available for use $215,300
Less: Raw materials inventory (12/31) 24,500
Direct materials used $190,800
Direct labor $114,500
Manufacturing overhead:
Indirect labor 19,600
Factory depreciation 37,900
Factory utilities 72,600
Total overhead 130,100
Total manufacturing cost $658,000
Total cost of work in process $658,000
Less: Work in process (12/31) 85,600
Cost of goods manufactured $572,400
What is the Schedule of Cost of Goods Manufactured?
The Schedule of Cost of Goods Manufactured shows the costs of:
- Beginning Work in Process
- Raw materials used
- Direct labor
- Overhead
- Less Ending Work in Process.
Thus, the Schedule of Cost of Goods Manufactured for Riverbed Company shows that the cost of goods manufactured for the period is $572,400.
Learn more about preparing the Schedule of Cost of Goods Manufactured at https://brainly.com/question/24257342
#SPJ1
We hope this information was helpful. Feel free to return anytime for more answers to your questions and concerns. We appreciate your visit. Our platform is always here to offer accurate and reliable answers. Return anytime. Your questions are important to us at Westonci.ca. Visit again for expert answers and reliable information.