Discover answers to your questions with Westonci.ca, the leading Q&A platform that connects you with knowledgeable experts. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform.

Diners are served in a process with two resources. The first resource has a capacity of 1.1 diners per hour. The capacity of the second resource is 1.5 diners per hour. Demand for this process is 0.9 diners per hour.Instruction: Round your answer to three decimal places. What is the cycle time of this process (in minutes)

Sagot :

The cycle time of this process for the firm is 2.89.

What is a Cycle Time?

This refers to the average time between the start of production of one unit and the start of production of the next unit of production

Cycle Time = Net time available to work / Customer demand

Cycle Time = 1.1 + 1.5 / 0.9

Cycle Time = 2.88888888889

Cycle Time = 2.89.

Therefore, the cycle time of this process for the firm is 2.89.

Read more about cycle time

brainly.com/question/18802868