Discover answers to your most pressing questions at Westonci.ca, the ultimate Q&A platform that connects you with expert solutions. Experience the convenience of finding accurate answers to your questions from knowledgeable professionals on our platform. Our platform provides a seamless experience for finding reliable answers from a network of experienced professionals.
Sagot :
Based on the costs given for PCB Corporation, the Variable costs per unit are:
- Variable cost per unit = $10
- Variable cost per unit for utilities = $0.60
- Variable cost per unit for maintenance = $0.30.
What are the variable costs per unit?
The variable cost per unit is:
= (Direct material + Direct labor + Indirect labor) / Units produced
= (7,500 + 18,000 + 4,500) / 3,000
= $10 per unit
The variable cost per unit for utilities is:
= (Total cost of utilities - Fixed portion of utilities cost) / Units produced
= (2,100 - 300) / 3,000
= $0.60
The variable cost per unit for maintenance is:
= (Total cost of maintenance - Fixed portion of maintenance cost) / Units produced
= (1,100 - 200) / 3,000
= $0.30
Find out more on variable cost per unit at https://brainly.com/question/5965421.
#SPJ1
Thanks for using our platform. We aim to provide accurate and up-to-date answers to all your queries. Come back soon. We hope you found what you were looking for. Feel free to revisit us for more answers and updated information. We're glad you chose Westonci.ca. Revisit us for updated answers from our knowledgeable team.