Get reliable answers to your questions at Westonci.ca, where our knowledgeable community is always ready to help. Ask your questions and receive precise answers from experienced professionals across different disciplines. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform.
Sagot :
Based on the costs given for PCB Corporation, the Variable costs per unit are:
- Variable cost per unit = $10
- Variable cost per unit for utilities = $0.60
- Variable cost per unit for maintenance = $0.30.
What are the variable costs per unit?
The variable cost per unit is:
= (Direct material + Direct labor + Indirect labor) / Units produced
= (7,500 + 18,000 + 4,500) / 3,000
= $10 per unit
The variable cost per unit for utilities is:
= (Total cost of utilities - Fixed portion of utilities cost) / Units produced
= (2,100 - 300) / 3,000
= $0.60
The variable cost per unit for maintenance is:
= (Total cost of maintenance - Fixed portion of maintenance cost) / Units produced
= (1,100 - 200) / 3,000
= $0.30
Find out more on variable cost per unit at https://brainly.com/question/5965421.
#SPJ1
Thanks for using our service. We aim to provide the most accurate answers for all your queries. Visit us again for more insights. We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. Thank you for trusting Westonci.ca. Don't forget to revisit us for more accurate and insightful answers.