Welcome to Westonci.ca, the place where your questions find answers from a community of knowledgeable experts. Get accurate and detailed answers to your questions from a dedicated community of experts on our Q&A platform. Experience the ease of finding precise answers to your questions from a knowledgeable community of experts.
Sagot :
Answer:
81 days
Step-by-step explanation:
Formula to solve this type of equation [tex]t=\frac{k}{p}[/tex]
t is time
k is a constant
p is people
We must substitute the values into the equation
[tex]54=\frac{k}{9}[/tex]
[tex]k=486[/tex]
Now we must substitute it to find the time
[tex]t=\frac{486}{6}[/tex]
you get 81
It would take [tex]6[/tex] builders [tex]36[/tex] days to complete the same house.
Who are builders?
Builders are those person whose job is to build or repair houses and other buildings.
We have,
[tex]9[/tex] builders take [tex]54[/tex] days to complete a house.
So,
[tex]1[/tex] builder will take [tex](\frac{54}{9})[/tex] days to complete a house,
In the same way,
[tex]6[/tex] builder will take [tex](\frac{54}{9}*6)[/tex] days to complete a house,
i.e.
[tex]6[/tex] builder [tex]=(\frac{54}{9}*6)= 36[/tex] days.
Hence, we can say that it would take [tex]6[/tex] builders [tex]36[/tex] days to complete the same house.
To know more about builders and work click here
https://brainly.com/question/16924313
#SPJ2
Thanks for stopping by. We are committed to providing the best answers for all your questions. See you again soon. We appreciate your visit. Our platform is always here to offer accurate and reliable answers. Return anytime. Westonci.ca is committed to providing accurate answers. Come back soon for more trustworthy information.