Welcome to Westonci.ca, the place where your questions are answered by a community of knowledgeable contributors. Get immediate and reliable answers to your questions from a community of experienced professionals on our platform. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform.

Compute the NPV for Project M if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project M Time: 0 1 2 3 4 5 Cash flow: −$2,400 $630 $760 $800 $880 $380 Should the project be accepted or rejected? multiple choice accepted rejected

Sagot :

The net present value is $305.73. The project should be accepted.

Net present value

Using this formula

Net present value=Cashflow÷(1+Cost of capital)^ time

Let plug in the formula

Net present value=-$2,400+ ($630÷(1+.09)^1) + ($760÷(1+.09)^2) + ($800÷(1+.09)^3) + ($880 ÷(1+.09)^4) + ($380÷(1+.09)^5)

Net present value=-$2,400+ ( $630÷(1.09)^1) + ($760÷(1.09)^2) + ($800÷(1.09)^3) + ($880 ÷(1.09)^4) + ($380÷(1.09)^5)

Net present value=-$2,400+ ($630÷1.09) + ($760÷1.1881) + ($800÷1.295029) + ($880 ÷1.41158161) + ($380÷1.538639549)

Net present value=-$2,400+ $577.98+$639.68+$617.75+623.41+$246.91

Net present value=$305.73

Based on the above calculation the project should be accepted.

Therefore the NPV is $305.73.

Learn more about net present value here:https://brainly.com/question/13228231

#SPJ1

We appreciate your visit. Our platform is always here to offer accurate and reliable answers. Return anytime. We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. Stay curious and keep coming back to Westonci.ca for answers to all your burning questions.