Welcome to Westonci.ca, where finding answers to your questions is made simple by our community of experts. Join our Q&A platform and connect with professionals ready to provide precise answers to your questions in various areas. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform.
Sagot :
Answer:
it takes 48 days for 15 men to work
it takes 16 days for 15/48*16
the answer is 5 men
Answer:
45 men
Step-by-step explanation:
If you 1/3 the amount of time (from 48 to 16 ) to weed the plot, you will need to TRIPLE the number of men to 45 men
We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. Keep exploring Westonci.ca for more insightful answers to your questions. We're here to help.