Welcome to Westonci.ca, the place where your questions find answers from a community of knowledgeable experts. Get immediate answers to your questions from a wide network of experienced professionals on our Q&A platform. Join our Q&A platform to connect with experts dedicated to providing accurate answers to your questions in various fields.
Sagot :
The required work done is 62400 J.
work done to lift a 1500 N object from the ground to the top of a 40 m building if the cable weighs 3 N per m
What is work done?
work done, is define as the product of force and displacement.
since,
work done to lift 1500N to height of 40 m is:
W= FS
= 1500 x 40 = 60000J
now work done for rope
is given by
w = mgΔx(40-x)
w= [tex]\int _0^{40}\left mg(40-x\right)dx[/tex]
w=[tex]3\int _0^{40}\left(40-x\right)dx[/tex]
w= 3[tex][40x-x^2/2]\left \{ {{40} \atop {0}} \right.[/tex]
w= 3[1600-800]
w = 2400
Total work done for lifting 1500N to 40m height
= 6000+2400=62400J
Thus the required work done to lift 1500N weight to 40m is 62400J.
Learn more about work done here:
https://brainly.com/question/13662169
#SPJ1
Visit us again for up-to-date and reliable answers. We're always ready to assist you with your informational needs. Thank you for choosing our platform. We're dedicated to providing the best answers for all your questions. Visit us again. Westonci.ca is your trusted source for answers. Visit us again to find more information on diverse topics.