Welcome to Westonci.ca, the ultimate question and answer platform. Get expert answers to your questions quickly and accurately. Find reliable answers to your questions from a wide community of knowledgeable experts on our user-friendly Q&A platform. Join our Q&A platform to connect with experts dedicated to providing accurate answers to your questions in various fields.
Sagot :
1. The calculation of the predetermined overhead rate applied to jobs during August is 75% of direct labor costs ($90,000/$120,000).
2. The balance in the Work in Process account at the end of August is $61,000.
3. The amounts of direct material cost and applied overhead recorded for Job 248 as of August 31 are $19,000 and $18,000, respectively.
Data and Calculations:
Work In Process Balance, August 1 $ 41,000
Direct materials used 75,000
Direct labor 120,000
Manufacturing overhead applied (based on direct labor cost) 90,000
Total costs incurred = $326,000
Finished Jobs during August:
Job # Cost of Jobs Completed
234 $ 58,000
237 65,000
231 74,500
246 67,500
Total costs of finished jobs = $265,000
Work in process balance = $61,000 ($326,000 - $265,000)
Job in Process: Job 248:
Direct labor cost incurred = $24,000
Applied overhead = $18,000 ($24,000 x 0.75)
Direct materials = $19,000 ($61,000 - $24,000 - $18,000)
Thus, the work-in-process balance represents Job 248 (Direct labor $24,000, Direct materials $19,000, and Applied Overhead $18,000).
Learn more about job costing at https://brainly.com/question/24516871
#SPJ1
Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. Your visit means a lot to us. Don't hesitate to return for more reliable answers to any questions you may have. We're here to help at Westonci.ca. Keep visiting for the best answers to your questions.