Welcome to Westonci.ca, where finding answers to your questions is made simple by our community of experts. Get quick and reliable solutions to your questions from knowledgeable professionals on our comprehensive Q&A platform. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.
Sagot :
1. The calculation of the predetermined overhead rate applied to jobs during August is 75% of direct labor costs ($90,000/$120,000).
2. The balance in the Work in Process account at the end of August is $61,000.
3. The amounts of direct material cost and applied overhead recorded for Job 248 as of August 31 are $19,000 and $18,000, respectively.
Data and Calculations:
Work In Process Balance, August 1 $ 41,000
Direct materials used 75,000
Direct labor 120,000
Manufacturing overhead applied (based on direct labor cost) 90,000
Total costs incurred = $326,000
Finished Jobs during August:
Job # Cost of Jobs Completed
234 $ 58,000
237 65,000
231 74,500
246 67,500
Total costs of finished jobs = $265,000
Work in process balance = $61,000 ($326,000 - $265,000)
Job in Process: Job 248:
Direct labor cost incurred = $24,000
Applied overhead = $18,000 ($24,000 x 0.75)
Direct materials = $19,000 ($61,000 - $24,000 - $18,000)
Thus, the work-in-process balance represents Job 248 (Direct labor $24,000, Direct materials $19,000, and Applied Overhead $18,000).
Learn more about job costing at https://brainly.com/question/24516871
#SPJ1
Thanks for using our service. We aim to provide the most accurate answers for all your queries. Visit us again for more insights. We appreciate your time. Please revisit us for more reliable answers to any questions you may have. Westonci.ca is your go-to source for reliable answers. Return soon for more expert insights.