Westonci.ca is the ultimate Q&A platform, offering detailed and reliable answers from a knowledgeable community. Explore comprehensive solutions to your questions from a wide range of professionals on our user-friendly platform. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.

Once the project schedule and project budget are approved they become the _____ Group of answer choices project plan derivative plan schedule plan baseline plan actual plan

Sagot :

Once the project schedule and project budget are approved they become the baseline plan. This is further explained below.

What is the baseline plan?

Generally,  Project management baselines are the established points from which further planning is done.

In conclusion, As soon as the project timeline and budget are greenlit, they constitute the foundation of the project.

Read more about baseline plan

https://brainly.com/question/21506960

#SPJ1

We hope this information was helpful. Feel free to return anytime for more answers to your questions and concerns. We hope our answers were useful. Return anytime for more information and answers to any other questions you have. Keep exploring Westonci.ca for more insightful answers to your questions. We're here to help.