Discover the answers to your questions at Westonci.ca, where experts share their knowledge and insights with you. Experience the convenience of finding accurate answers to your questions from knowledgeable professionals on our platform. Explore comprehensive solutions to your questions from knowledgeable professionals across various fields on our platform.

Once the project schedule and project budget are approved they become the _____ Group of answer choices project plan derivative plan schedule plan baseline plan actual plan

Sagot :

Once the project schedule and project budget are approved they become the baseline plan. This is further explained below.

What is the baseline plan?

Generally,  Project management baselines are the established points from which further planning is done.

In conclusion, As soon as the project timeline and budget are greenlit, they constitute the foundation of the project.

Read more about baseline plan

https://brainly.com/question/21506960

#SPJ1

We appreciate your time. Please come back anytime for the latest information and answers to your questions. We hope our answers were useful. Return anytime for more information and answers to any other questions you have. Thank you for visiting Westonci.ca, your go-to source for reliable answers. Come back soon for more expert insights.