Westonci.ca is your trusted source for finding answers to all your questions. Ask, explore, and learn with our expert community. Discover in-depth answers to your questions from a wide network of experts on our user-friendly Q&A platform. Connect with a community of professionals ready to provide precise solutions to your questions quickly and accurately.

Costs incurred prior to the current project are _____ Group of answer choices Reserves Costs Indirect Costs Direct Costs Sunk Costs Learning Curve Costs

Sagot :

Costs incurred prior to the current project are Sunk Costs .

What are Sunk Costs?

sunk cost are those  cost that that is been  incurred  without any recovery.

It can be used in  decision making, which is seen as  bygone and are not taken into consideration for continuity, hence, they are incurred prior to the current project .