Find the best solutions to your questions at Westonci.ca, the premier Q&A platform with a community of knowledgeable experts. Get detailed and accurate answers to your questions from a community of experts on our comprehensive Q&A platform. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform.
Sagot :
The answer is Bottom-Up estimates.
Bottom-up estimating involves the estimation of work at the lowest possible level of detail.
The estimates so calculated are then aggregated to arrive at summary totals. The probability to meet the estimated amounts improves substantially by building detailed cost and time estimates for a work package.
In other words, bottom-up estimating approximates an overall value by approximating values for smaller items and using the sum of these values as the overall value.
This cost estimation tool is often used when detailed information is available about lower-level activities. It can be especially useful when estimating projects that are similar to ones that were completed in the past.
Hence, a Bottom-Up estimate is a cost estimation tool that involves estimating individual work items or activities and summing them to get a project total.
Learn more about Cost:
https://brainly.com/question/25109150
#SPJ4
Thanks for stopping by. We are committed to providing the best answers for all your questions. See you again soon. We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. Discover more at Westonci.ca. Return for the latest expert answers and updates on various topics.