Get the answers you need at Westonci.ca, where our expert community is dedicated to providing you with accurate information. Get immediate answers to your questions from a wide network of experienced professionals on our Q&A platform. Experience the convenience of finding accurate answers to your questions from knowledgeable experts on our platform.
Sagot :
The longest path in the project network is the critical path.
Critical Path is an estimate of the minimal (shortest) project duration and is the longest path through the project network diagram.
Since there is no (positive) float or wiggle space on the Critical Way, it is the longest path through the project. On the timetable network diagram, there is (positive) float or leeway for other (non-critical) paths.
Because the Critical Path is the only path that runs continuously from beginning to conclusion of the project, with no float or wiggle room to cut down, it is also an estimate of the minimal (shortest) duration to accomplish the project. Other paths contain float or wiggle room, but cutting those courses won't speed up the completion of your job.
The Critical Path must be shortened in order to reduce the project timeline, and this can be done by applying schedule compression strategies like Fast-tracking and Crashing.
Learn more about critical path here
https://brainly.com/question/14036336
#SPJ4
Thank you for your visit. We're dedicated to helping you find the information you need, whenever you need it. We appreciate your time. Please revisit us for more reliable answers to any questions you may have. Discover more at Westonci.ca. Return for the latest expert answers and updates on various topics.