Welcome to Westonci.ca, where you can find answers to all your questions from a community of experienced professionals. Experience the convenience of getting reliable answers to your questions from a vast network of knowledgeable experts. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform.

The Critical Path is: Group of answer choices the interrelationships of project activities. the shortest path in the project network. the most important identified tasks within the project. the longest path in the project network. the longest time in which the project can be completed.

Sagot :

The longest path in the project network is the critical path.

Critical Path is an estimate of the minimal (shortest) project duration and is the longest path through the project network diagram.

Since there is no (positive) float or wiggle space on the Critical Way, it is the longest path through the project. On the timetable network diagram, there is (positive) float or leeway for other (non-critical) paths.

Because the Critical Path is the only path that runs continuously from beginning to conclusion of the project, with no float or wiggle room to cut down, it is also an estimate of the minimal (shortest) duration to accomplish the project. Other paths contain float or wiggle room, but cutting those courses won't speed up the completion of your job.

The Critical Path must be shortened in order to reduce the project timeline, and this can be done by applying schedule compression strategies like Fast-tracking and Crashing.

Learn more about critical path here