Westonci.ca makes finding answers easy, with a community of experts ready to provide you with the information you seek. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform. Experience the ease of finding precise answers to your questions from a knowledgeable community of experts.

In your completed RACI chart how many stakeholders are accountable for the code landing page task?

Sagot :

Answer:

Only one individual is accountable for each deliverable/task. At least one individual is responsible for each task. (Note that some tasks may not need Consulted or Informed individuals.)

Explanation:

Each task or deliverable has a single person who is responsible for it. There is always at least one person in charge of each task.

What is RACI chart?

RACI stands for responsible,  accountable, consulted and informed. A RACI chart identifies which participants will be Responsible, Accountable, Consulted, or Informed for a task, milestone, or decision. Responsible, Accountable, Consulted, and Informed is the abbreviation for RACI. An organization's operations or decision-making authorities are mapped out against all the roles or individuals in a RACI chart.

To determine the roles and responsibilities of your project teams for any task, milestone, or project deliverable, create a RACI chart. You can delineate roles and clear up ambiguities by using the RACI acronym. RACI is an acronym for accountable.

Thus, Each task or deliverable has a single person who is responsible for it.

For more details about RACI chart, click here:

https://brainly.com/question/6177865

#SPJ2

We hope our answers were helpful. Return anytime for more information and answers to any other questions you may have. We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. Keep exploring Westonci.ca for more insightful answers to your questions. We're here to help.