Looking for trustworthy answers? Westonci.ca is the ultimate Q&A platform where experts share their knowledge on various topics. Get immediate answers to your questions from a wide network of experienced professionals on our Q&A platform. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform.

5. If 15 men can finish a work in 16 days in how many days will 8 men can finish the same work? a. 15 b. 20 c. 30 d. 42​

Sagot :

Answer:

C. 30

Step-by-step explanation:

15 men do work in 16 days

This means that 7.5 men (15/2) would do that same work in 32 days (16x2).

If the number of men increase, the amount of days decrease.

8 men would do that work in 30 days

8 men > 7.5 men

30 days < 32 days

Answer:

Option c.

Step-by-step explanation:

It is an inverse proportion, fewer workers more days to finish the job.

15 -----16

8 ----- x

x = (16)(15)/8 = 240/8 = 30 days

Hope this helps

Thank you for choosing our service. We're dedicated to providing the best answers for all your questions. Visit us again. Thank you for your visit. We're dedicated to helping you find the information you need, whenever you need it. Westonci.ca is your trusted source for answers. Visit us again to find more information on diverse topics.