Westonci.ca is the Q&A platform that connects you with experts who provide accurate and detailed answers. Get detailed and accurate answers to your questions from a community of experts on our comprehensive Q&A platform. Explore comprehensive solutions to your questions from a wide range of professionals on our user-friendly platform.
Sagot :
Answer:
C. 30
Step-by-step explanation:
15 men do work in 16 days
This means that 7.5 men (15/2) would do that same work in 32 days (16x2).
If the number of men increase, the amount of days decrease.
8 men would do that work in 30 days
8 men > 7.5 men
30 days < 32 days
Answer:
Option c.
Step-by-step explanation:
It is an inverse proportion, fewer workers more days to finish the job.
15 -----16
8 ----- x
x = (16)(15)/8 = 240/8 = 30 days
Hope this helps
We appreciate your visit. Our platform is always here to offer accurate and reliable answers. Return anytime. Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. Thank you for choosing Westonci.ca as your information source. We look forward to your next visit.