Welcome to Westonci.ca, the ultimate question and answer platform. Get expert answers to your questions quickly and accurately. Discover in-depth solutions to your questions from a wide range of experts on our user-friendly Q&A platform. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.
Sagot :
The better Project is Project S having a NPV of $17.968 and IRR of 12.10 %
IRR:
- An approach to capital budgeting that is used to assess the profitability of a project is the discounted payback time. Internal rate of return is one of these capital planning strategies (IRR).
- This rate of return corresponds to the point at which a project's net present value equals zero. Since it does not account for any outside forces, such as inflation, they call it internal.
The calculator's capabilities will be utilized to determine the IRR,
Project S
- CF0 = (1,000)
- CF1 = 882.62 & F01 = 1
- CF2 = 250 & F02 = 1
- CF3 = 15 & F03 = 1
- CF4 = 5 & F04 = 1
- I = 10.5%
- [NPV] [CPT]
- The NPV is $17.968
- [IRR] [CPT]
- The IRR will come as 12.10%
- Project L
- CF0 = (1,000)
- CF1 = 0 & F01 = 1
- CF2 = 260 & F02 = 1
- CF3 = 420 & F03 = 1
- CF4 = 732.87 & F04 = 1
- I = 10.5%
- [NPV] [CPT]
- The NPV is $15.78
- [IRR] [CPT]
- The IRR will come as 11.03%
- The better Project is Project S having a NPV of $17.968 and IRR of 12.10%
Learn more about IRR here brainly.com/question/7920964
#SPJ4
Thanks for using our platform. We aim to provide accurate and up-to-date answers to all your queries. Come back soon. Thank you for choosing our platform. We're dedicated to providing the best answers for all your questions. Visit us again. Thank you for choosing Westonci.ca as your information source. We look forward to your next visit.