Welcome to Westonci.ca, the ultimate question and answer platform. Get expert answers to your questions quickly and accurately. Experience the ease of finding reliable answers to your questions from a vast community of knowledgeable experts. Our platform offers a seamless experience for finding reliable answers from a network of knowledgeable professionals.
Sagot :
The better Project is Project S having a NPV of $17.968 and IRR of 12.10 %
IRR:
- An approach to capital budgeting that is used to assess the profitability of a project is the discounted payback time. Internal rate of return is one of these capital planning strategies (IRR).
- This rate of return corresponds to the point at which a project's net present value equals zero. Since it does not account for any outside forces, such as inflation, they call it internal.
The calculator's capabilities will be utilized to determine the IRR,
Project S
- CF0 = (1,000)
- CF1 = 882.62 & F01 = 1
- CF2 = 250 & F02 = 1
- CF3 = 15 & F03 = 1
- CF4 = 5 & F04 = 1
- I = 10.5%
- [NPV] [CPT]
- The NPV is $17.968
- [IRR] [CPT]
- The IRR will come as 12.10%
- Project L
- CF0 = (1,000)
- CF1 = 0 & F01 = 1
- CF2 = 260 & F02 = 1
- CF3 = 420 & F03 = 1
- CF4 = 732.87 & F04 = 1
- I = 10.5%
- [NPV] [CPT]
- The NPV is $15.78
- [IRR] [CPT]
- The IRR will come as 11.03%
- The better Project is Project S having a NPV of $17.968 and IRR of 12.10%
Learn more about IRR here brainly.com/question/7920964
#SPJ4
We appreciate your time. Please come back anytime for the latest information and answers to your questions. We hope you found what you were looking for. Feel free to revisit us for more answers and updated information. Stay curious and keep coming back to Westonci.ca for answers to all your burning questions.