Answer: Bac = 200 ; pv = 100 ac = 120 ; ev = 80 assuming that what the project has experienced to date can be expected to continue in the future, the variance at completion is 300.
Explanation: The formula used when current variances are expected to continue (typical variances) is: BAC/CPI. CPI=EV/AC = 80/120 = .666 Solved, that is: 200/0.666 = 300
Cost management is the process of planning and controlling the costs associated with running a business. It includes collecting, analyzing and reporting cost information to more effectively budget, forecast and monitor costs.
Cost management practices can be applied to specific projects or to the company's overall operating model. Cost management typically focuses on generating savings and maximizing profits in the longer term.
To know more about cost management click on the link below
https://brainly.in/question/13007947
#SPJ4