Welcome to Westonci.ca, the place where your questions are answered by a community of knowledgeable contributors. Discover a wealth of knowledge from professionals across various disciplines on our user-friendly Q&A platform. Connect with a community of professionals ready to provide precise solutions to your questions quickly and accurately.

What are some indicators that may support the need for an over target baseline/over target schedule?

Sagot :

The primary goal of implementing an over target schedule is to increase management control over the remaining project. While it results in a new baseline that is now higher than the contract budget base, it has been shown to improve control over the remaining contract work. Thus exceeds contract target cost is referred to as an Over Target Baseline.

A Total Allocated Budget (TAB) that has been formally reprogrammed to include additional performance management budget. It is calculated by combining the Contract Budget Base (CBB) and any additional performance management budgets. An over target schedule (OTS) is a condition in which a baseline schedule is time-phased beyond the contract completion date.

To learn more about management, click here.

https://brainly.com/question/14523862

#SPJ4

We hope this was helpful. Please come back whenever you need more information or answers to your queries. We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. Westonci.ca is here to provide the answers you seek. Return often for more expert solutions.