Discover the answers you need at Westonci.ca, a dynamic Q&A platform where knowledge is shared freely by a community of experts. Get expert answers to your questions quickly and accurately from our dedicated community of professionals. Join our platform to connect with experts ready to provide precise answers to your questions in different areas.

What are some indicators that may support the need for an over target baseline/over target schedule?

Sagot :

The primary goal of implementing an over target schedule is to increase management control over the remaining project. While it results in a new baseline that is now higher than the contract budget base, it has been shown to improve control over the remaining contract work. Thus exceeds contract target cost is referred to as an Over Target Baseline.

A Total Allocated Budget (TAB) that has been formally reprogrammed to include additional performance management budget. It is calculated by combining the Contract Budget Base (CBB) and any additional performance management budgets. An over target schedule (OTS) is a condition in which a baseline schedule is time-phased beyond the contract completion date.

To learn more about management, click here.

https://brainly.com/question/14523862

#SPJ4