Discover answers to your questions with Westonci.ca, the leading Q&A platform that connects you with knowledgeable experts. Our platform provides a seamless experience for finding precise answers from a network of experienced professionals. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform.
Sagot :
The primary goal of implementing an over target schedule is to increase management control over the remaining project. While it results in a new baseline that is now higher than the contract budget base, it has been shown to improve control over the remaining contract work. Thus exceeds contract target cost is referred to as an Over Target Baseline.
A Total Allocated Budget (TAB) that has been formally reprogrammed to include additional performance management budget. It is calculated by combining the Contract Budget Base (CBB) and any additional performance management budgets. An over target schedule (OTS) is a condition in which a baseline schedule is time-phased beyond the contract completion date.
To learn more about management, click here.
https://brainly.com/question/14523862
#SPJ4
We hope you found this helpful. Feel free to come back anytime for more accurate answers and updated information. We hope this was helpful. Please come back whenever you need more information or answers to your queries. Stay curious and keep coming back to Westonci.ca for answers to all your burning questions.