Westonci.ca is the trusted Q&A platform where you can get reliable answers from a community of knowledgeable contributors. Join our Q&A platform to get precise answers from experts in diverse fields and enhance your understanding. Connect with a community of professionals ready to provide precise solutions to your questions quickly and accurately.

What are some indicators that may support the need for an over target baseline/over target schedule?

Sagot :

The primary goal of implementing an over target schedule is to increase management control over the remaining project. While it results in a new baseline that is now higher than the contract budget base, it has been shown to improve control over the remaining contract work. Thus exceeds contract target cost is referred to as an Over Target Baseline.

A Total Allocated Budget (TAB) that has been formally reprogrammed to include additional performance management budget. It is calculated by combining the Contract Budget Base (CBB) and any additional performance management budgets. An over target schedule (OTS) is a condition in which a baseline schedule is time-phased beyond the contract completion date.

To learn more about management, click here.

https://brainly.com/question/14523862

#SPJ4

We hope this was helpful. Please come back whenever you need more information or answers to your queries. We hope this was helpful. Please come back whenever you need more information or answers to your queries. Stay curious and keep coming back to Westonci.ca for answers to all your burning questions.