Discover a world of knowledge at Westonci.ca, where experts and enthusiasts come together to answer your questions. Discover detailed solutions to your questions from a wide network of experts on our comprehensive Q&A platform. Connect with a community of professionals ready to provide precise solutions to your questions quickly and accurately.

A(n) ________ constraint addresses the sequence in which project activities must occur even after considering resource constraints.

Sagot :

A technical or logic constraint addresses the sequence in which project activities must occur even after considering resource constraints.

Technology-associated circumstance or maybe that stops the assignment from completely turning in an appropriate way to customers and end users.

Logical constraints are one precise form of discrete or numerical Constraints.

It sincerely way the cease-to-end manner of moving and storing elements of completed and unfinished items. as instance, a vehicle production employer will shop and transfer motors (or their parts) in a systematic way.

Operations control consists of three stages: strategic, tactical, and operational.

Learn more about operation management here

https://brainly.com/question/1382997

#SPJ4