Get the answers you need at Westonci.ca, where our expert community is always ready to help with accurate information. Get accurate and detailed answers to your questions from a dedicated community of experts on our Q&A platform. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform.

Which three roles are most responsible for ensuring successful execution at the large solution level?

Sagot :

Large solution safe uses 3 predominant activities to help coordinate multiple ARTs and suppliers: Pre- and post-PI planning – Pre- and submit-PI making plans are used to put together for, and comply with up after, program Increment (PI) planning for arts and suppliers in a solution train.

Solution trains coordinate the development of solutions within a PI, and they provide for cadence and synchronization of ARTs and providers, including PI planning activities and the answer demo.

Specs, designs, and exams – knowledge of each the current and future states may be captured in any form appropriate—as long because it consists of the three primary elements: specifications (documented definition of system behavior), layout, and exams.

Learn more about synchronization here: https://brainly.com/question/14389182