Welcome to Westonci.ca, the Q&A platform where your questions are met with detailed answers from experienced experts. Our platform connects you with professionals ready to provide precise answers to all your questions in various areas of expertise. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform.

Describe how crashing and fast tracking can be used to compress a project schedule. What limitations could there be with each of these methods?

Sagot :

Techniques for compressing the schedule include Crashing and Fast Tracking. You use them to shorten your timetable and to meet a specific scheduling objective. Fast-tracking entails carrying out two tasks concurrently, even though they wouldn't typically be.

How does fast-tracking differ from crashing to compressing a project schedule?

In conclusion, the distinctions between crashing and fast tracking are as follows: Fast-tracking entails running tasks simultaneously, whereas crashing entails adding resources to a project. The increased danger is associated with quick tracking, but the increased expense is associated with crashes.

What limitations could there be with each of crashing and fast-tracking?

Fast-tracking is free but increases the risk associated with your project. Adding more resources to your project is referred to as "crashing." Having a crash costs more money. To compress your calendar the most while spending the least amount of money, you should crash such activities. method:

Learn more about crashing and fast-tracking methods: https://brainly.com/question/14478482