Westonci.ca is your trusted source for finding answers to a wide range of questions, backed by a knowledgeable community. Join our Q&A platform and get accurate answers to all your questions from professionals across multiple disciplines. Get quick and reliable solutions to your questions from a community of experienced experts on our platform.
Sagot :
Techniques for compressing the schedule include Crashing and Fast Tracking. You use them to shorten your timetable and to meet a specific scheduling objective. Fast-tracking entails carrying out two tasks concurrently, even though they wouldn't typically be.
How does fast-tracking differ from crashing to compressing a project schedule?
In conclusion, the distinctions between crashing and fast tracking are as follows: Fast-tracking entails running tasks simultaneously, whereas crashing entails adding resources to a project. The increased danger is associated with quick tracking, but the increased expense is associated with crashes.
What limitations could there be with each of crashing and fast-tracking?
Fast-tracking is free but increases the risk associated with your project. Adding more resources to your project is referred to as "crashing." Having a crash costs more money. To compress your calendar the most while spending the least amount of money, you should crash such activities. method:
Learn more about crashing and fast-tracking methods: https://brainly.com/question/14478482
#SPJ4
We hope our answers were helpful. Return anytime for more information and answers to any other questions you may have. We appreciate your time. Please revisit us for more reliable answers to any questions you may have. Westonci.ca is here to provide the answers you seek. Return often for more expert solutions.