Welcome to Westonci.ca, where finding answers to your questions is made simple by our community of experts. Get immediate and reliable answers to your questions from a community of experienced professionals on our platform. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform.

F jackson collectibles, inc. has a safety stock of 35 units and the average weekly demand is 14 units, how many days can be covered if the shipment from the supplier is delayed ?

Sagot :

17.5 Days can be covered if the shipment from the supplier is delayed.

What Average Demand?

Average demand, which is calculated by dividing the total number of kilowatt-hours by the number of units of time in the interval, is the demand for the electrical system or any of its components throughout a specific period of time with a long length.

According to the information:

35 items make up Jackson Collectibles' safety supply.

However, 14 units are needed each week.

The amount of weeks they may survive on safety stock as a result is:

= Weekly demand / safety stock

= 35 / 14

= 2.5 weeks

These are in days:

= 2.5 * 7

= 17.5 days

To know more about Average demand visit:

https://brainly.com/question/24260192

#SPJ4

Thanks for using our platform. We aim to provide accurate and up-to-date answers to all your queries. Come back soon. Thanks for stopping by. We strive to provide the best answers for all your questions. See you again soon. Find reliable answers at Westonci.ca. Visit us again for the latest updates and expert advice.