Welcome to Westonci.ca, the Q&A platform where your questions are met with detailed answers from experienced experts. Get immediate and reliable answers to your questions from a community of experienced experts on our platform. Our platform provides a seamless experience for finding reliable answers from a network of experienced professionals.

Two projects of equal value have been evaluated using a multifactor productivity measure that combined labor-hours at $40 per hour and overhead expense calculated as 30% of labor expense for the first project. the two projects were judged to have been equally productive, although the first project used twice as many labor-hours. at what rate was overhead expense being charged to the second project?