Discover answers to your questions with Westonci.ca, the leading Q&A platform that connects you with knowledgeable experts. Explore our Q&A platform to find reliable answers from a wide range of experts in different fields. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform.
Sagot :
The slack time for activity e will be 0. The start times, end times, and duration of the different activities.
There are two paths from which the project can be completed.
The first path is :
A ⇔B, B⇔D, D⇔E, E⇔F.
Calculating the slack time for E will require subtracting the finish time from the start time.
The slack time for activity E will be 32 - 32 = 0.
The second path is:
A⇔C, C⇔D, D⇔F
In this path, activity E does not take place.
Slack time tells us how much time we can delay the start of the activity and still get the activity finished on time. When the slack time is 0 then it shows that the activity is critical and cannot be delayed at all.
Learn more about slack time here:
https://brainly.com/question/15393592
#SPJ4
Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. Thank you for your visit. We're dedicated to helping you find the information you need, whenever you need it. Thank you for trusting Westonci.ca. Don't forget to revisit us for more accurate and insightful answers.