Get the answers you need at Westonci.ca, where our expert community is dedicated to providing you with accurate information. Discover solutions to your questions from experienced professionals across multiple fields on our comprehensive Q&A platform. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform.
Sagot :
The slack time for activity e will be 0. The start times, end times, and duration of the different activities.
There are two paths from which the project can be completed.
The first path is :
A ⇔B, B⇔D, D⇔E, E⇔F.
Calculating the slack time for E will require subtracting the finish time from the start time.
The slack time for activity E will be 32 - 32 = 0.
The second path is:
A⇔C, C⇔D, D⇔F
In this path, activity E does not take place.
Slack time tells us how much time we can delay the start of the activity and still get the activity finished on time. When the slack time is 0 then it shows that the activity is critical and cannot be delayed at all.
Learn more about slack time here:
https://brainly.com/question/15393592
#SPJ4
Thanks for using our service. We're always here to provide accurate and up-to-date answers to all your queries. Thanks for stopping by. We strive to provide the best answers for all your questions. See you again soon. Thank you for visiting Westonci.ca, your go-to source for reliable answers. Come back soon for more expert insights.