Get the answers you need at Westonci.ca, where our expert community is dedicated to providing you with accurate information. Discover in-depth solutions to your questions from a wide range of experts on our user-friendly Q&A platform. Discover in-depth answers to your questions from a wide network of professionals on our user-friendly Q&A platform.

Jack Simpson, contract negotiator for Nebula Airframe Company, is currently involved in bidding on a follow-up government contract. In gathering cost data from the first three units, which Nebula produced under a research and development contract, he found that the first unit took 2,000 labor hours, the second took 1,700 labor hours, and the third took 1,600 hours. Use Exhibit 4A.6.

In a contract for three more units, how many labor hours should Simpson plan for? (Round your answer to the nearest whole number.)