Explore Westonci.ca, the premier Q&A site that helps you find precise answers to your questions, no matter the topic. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform. Explore comprehensive solutions to your questions from knowledgeable professionals across various fields on our platform.

Acme widgets had an order to process 250 widgets. The first unit required 200 minutes to assemble. Before starting, the company estimated the amount of time it would require to assemble all 250 widgets if they learned at an 85% rate. After assembling all 250 widgets, acme realized they had learned at an 80% rate. How much time less than their estimate did acme take? you should be able to compute the answer within plus or minus 2 hours. Group of answer choices 296. 1 hours 126. 6 hours 140. 3 hours 91. 2 hours 155. 8 hours.