Looking for answers? Westonci.ca is your go-to Q&A platform, offering quick, trustworthy responses from a community of experts. Experience the convenience of getting reliable answers to your questions from a vast network of knowledgeable experts. Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform.

the​ farm-4-less tractor company produces a grain combine​ (gc) in addition to both a large​ (lt) and small size tractor​ (sm). its production manager desires to produce to customer demand using a mixed model production line. the current sequence of​ production, which is repeated times during a​ shift, is: ​-​-​-​-​- a new machine is produced every minutes. the plant operates two​ eight-hour shifts. there is no downtime because the​ four-hours between each shift are dedicated to maintenance and restocking raw material. based on this​ information, answer the following questions. part 2 a. how long does it take the production cycle to be​ completed? the cycle sequence is completed in enter your response here minutes. ​(enter your response as a whole​ number.) part 3 b. how many of each type of machine does​ farm-4-less produce in a​ shift? ​(enter your responses as whole​ numbers.) type quantity in a shift sm enter your response here lt enter your response here gc enter your response here