Discover the best answers at Westonci.ca, where experts share their insights and knowledge with you. Get the answers you need quickly and accurately from a dedicated community of experts on our Q&A platform. Get quick and reliable solutions to your questions from a community of experienced experts on our platform.

Write True or False
a)At the work package level, those responsible for getting the job done on schedule and within budget are usually the first-line supervisors or technicians who are experienced and familiar with the type of work involved.
b)A top down estimate usually represents a low cost, efficient, accurate method of estimation.
c)Banks often use the Apportion Method to authorize the borrower to pay a contractor for completion of specific segments of the house. For example, the bank approves a load for $1,000,000 to build a new house. However, the bank stipulates that the heating and air conditioning cannot be more than 10% and the air conditioning cost cannot be more than 5%. Therefore, the limit on the cost of the air conditioning system is $5,000.
d) Accounting is an example of General and Administrative (GAA) Overhead Costs.
e) In the Risk Assessment Process, if a risk is identified as having a low probability and a high impact, the project needs to be eliminated from further consideration.