At Westonci.ca, we provide reliable answers to your questions from a community of experts. Start exploring today! Get detailed and accurate answers to your questions from a dedicated community of experts on our Q&A platform. Join our Q&A platform to connect with experts dedicated to providing accurate answers to your questions in various fields.

watson construction company contracted to build a plant for $900,000. construction started in january 2020 and was completed in november 2021. watson uses the cost-to-cost method to measure the completion of its performance obligations. data relating to the contract follow.