Westonci.ca is your trusted source for finding answers to all your questions. Ask, explore, and learn with our expert community. Discover in-depth solutions to your questions from a wide range of experts on our user-friendly Q&A platform. Get immediate and reliable solutions to your questions from a community of experienced professionals on our platform.
Sagot :
SOLUTION
Given the question in the question tab, the following are the solution steps to answer the question
STEP 1: Write the rate at which the construction crew built the road
[tex]1\text{ day = }3\frac{1}{5}km[/tex]STEP 2: Calculate the total length of road they built
[tex]\begin{gathered} 1\text{ day = }3\frac{1}{5} \\ 2\frac{3}{8}\text{days = x length of road} \\ \text{Converting the mixed fraction to improper fraction, we have:} \\ 3\frac{1}{5}=\frac{(3\times5)+1}{5}=\frac{15+1}{5}=\frac{16}{5} \\ 2\frac{3}{8}=\frac{(8\times2)+3}{8}=\frac{16+3}{8}=\frac{19}{8} \\ \\ \text{ Rewriting the equation, we have:} \\ 1\text{day}=\frac{16}{5}km \\ \frac{19}{8}=x\text{ km} \\ By\text{ cross multiplying, we have;} \\ x\times1=\frac{16}{5}\times\frac{19}{8} \\ x=\frac{304}{40}km=\frac{38}{5} \\ \text{Converting to mixed fraction, we have:} \\ 7\frac{3}{5}km \end{gathered}[/tex]Hence, the total length of road built by the construction crew in 2 3/8 days is:
[tex]7\frac{3}{5}km[/tex]
We hope this information was helpful. Feel free to return anytime for more answers to your questions and concerns. We appreciate your visit. Our platform is always here to offer accurate and reliable answers. Return anytime. Find reliable answers at Westonci.ca. Visit us again for the latest updates and expert advice.