Get the answers you need at Westonci.ca, where our expert community is dedicated to providing you with accurate information. Discover reliable solutions to your questions from a wide network of experts on our comprehensive Q&A platform. Get quick and reliable solutions to your questions from a community of experienced experts on our platform.

20MEBuilding BarnsPOW ID: 5179ProblemPrintThe workers at Amy's Bam Company usually work in teams of 5. Ittakes a crew of 5 workers 9 days to build a bamA crew lost two of its workers. How many days should it take theremaining 3 workers to build a barn?ExtraExtra: If a customer eeds to have a bam built in 7 days, what is the minimum number of workers that Amywould need to put on the job?

Sagot :

We have the next information

If with 5 works take 9 days to build a barn, then only one worker will take five times the time given(9 days), therefore if have that 1 worker will take 45 days to build a barn

then we divide 45 between 3 in order to know how many days will take to build a barn for 3 workers

[tex]x=\frac{45}{3}=15[/tex]

to 3 workers will take 15 days to build a barn

If the customer needs to barn a build-in 7 days

[tex]x=\frac{45}{7}=6.42=7[/tex]

we will need 7 workers to build a barn in 7 days