Welcome to Westonci.ca, the ultimate question and answer platform. Get expert answers to your questions quickly and accurately. Connect with a community of experts ready to provide precise solutions to your questions quickly and accurately. Join our platform to connect with experts ready to provide precise answers to your questions in different areas.

Preparing an estimate for a construction job, a carpenter assumes about a 13% waste factor. If the finished project contains 1280 linear feet of boards, how many linear feet should the carpenter order? (Hint: If the waste is 13%,then the finished product is 100% - 13% or 87% of the total order.)

Sagot :

Answer:

Explanation:

From the information given,

waste factor = 13%

Finished project = 100 - 13 = 87%

Let x represent the number of linear feet of boards that the carpenter should order.

If the finished project contains 1280 linear feet of boards, it means that

87% of x = 1280

Thus,

87/100 * x = 1280

0.87x = 1280

x = 1280/0.87

x = 1471.26

Approximately, 1471 linear feet of boards should be ordered