Discover answers to your most pressing questions at Westonci.ca, the ultimate Q&A platform that connects you with expert solutions. Join our platform to connect with experts ready to provide detailed answers to your questions in various areas. Get quick and reliable solutions to your questions from a community of experienced experts on our platform.
Sagot :
The total standard cost for one unit of product that would appear on a standard cost card = $ 6.8
Standard cost :
A standard cost is the calculated cost of a regular manufacturing process against which factual costs are compared. Of course, if a new product, service, or process is to be carried out, the original standard costs will have to be estimated. Standard cost is a system of account that uses destined standard costs for direct material, direct labor, and plant charges. Standard cost is the alternate cost control fashion, the first being popular control. It's also one of the most lately developed advances of cost account
Giving the required information:
Ship Co. produces storage crates that require 23.0 meters of material at $0.10 per meter and 0.15 direct labor hours at $16.00 per hour. Overhead is applied at the rate of $14 per direct labor hour.
Direct material= 23 ×0.10= $2.3
Direct labor= 16 × 0.15 = $2.4
Overhead= 0.15 × 14= $ 2.1
Total unitary cost= $2.3 + $2.4 + $2.1
= $ 6.8
Unitary cost :
The unitary cost is the fee incurred by a company to have, store and vend one unit of a individual product. Unitary costs contain all fixed costs and all flexible costs concerned in product.
Learn more about standard cost :
brainly.com/question/24174272
#SPJ4
Thank you for visiting. Our goal is to provide the most accurate answers for all your informational needs. Come back soon. We appreciate your visit. Our platform is always here to offer accurate and reliable answers. Return anytime. Get the answers you need at Westonci.ca. Stay informed by returning for our latest expert advice.