Welcome to Westonci.ca, the place where your questions are answered by a community of knowledgeable contributors. Get the answers you need quickly and accurately from a dedicated community of experts on our Q&A platform. Get precise and detailed answers to your questions from a knowledgeable community of experts on our Q&A platform.
Sagot :
The answer is false. Liquidated damages exist when the sum agreed upon by all parties is a genuine estimate project of the harm caused by a future violation of contract.
As a result, all contract parties agree that the amount is fair compensation for the project. A contractor who fails to complete a construction project on time and is charged daily until the job is completed is an example of liquidated damages. discusses unliquidated damages that occur in the ordinary run of business, i.e. actual damages sustained as a result of violation of contract describes liquidated damages, which both parties anticipated before entering into the contract and would be paid in the event of a breach.
To learn more about liquidated, click here.
https://brainly.com/question/20922015
#SPJ4
Thank you for choosing our service. We're dedicated to providing the best answers for all your questions. Visit us again. We hope you found what you were looking for. Feel free to revisit us for more answers and updated information. Stay curious and keep coming back to Westonci.ca for answers to all your burning questions.